Dear All, Am workig new project, I need to take factory licence. Please let me know wat r the documents required to submit alongwith application as it is chemical industry.
From India, Pune
From India, Pune
Dear member,
Please refer the following document required.
- Form 1A (Certificate of Stability issued by qualified structural engineer) (in duplicate)
- Flow chart of the manufacturing process (in Triplicate)
- Land or Site Possession Certificate ( in duplicate )
- Certificate from Controller of Explosives (wherever explosive substances are stored or used) ( in duplicate )
- Treasury Receipted Chillan for having paid the prescribed fee of for Factories proposed
- Questionnaire Form duly filled and signed( in duplicate )
- Clearance certificate from the Pollution Control Board. (in duplicate )
- Application in Form No.1 (in duplicate).
- Registration application inForm No.2 duly filled with all particulars and signed by the occupier and the manager. (In Triplicate)
- List of directors /
- Partners with the memorandum of article of association / partnership deed (in Duplicate)
- Prescribed Fee paid challan
- Health and Safety policy of the proposed factory drawn and duly signed by the
Occupier in case of factories engaged in the hazardous processes.
Regards,
Varun
9845434343
From India, Bangalore