Dear sir, Kindly tell me in my company there are 50 employees and their working hours is 8. but sometimes some of them do work more which is not more than one hour each .. so some of them work 9 hour which counts as their overtime suppose 35 workers worked 8 hours in a day and remaining 15 workers worked 9 hours in a day than how can we calculate mandays?
From United Arab Emirates, Abu Dhabi
abbasiti
517

Dear Saqibhse, If 35 worked for 8 hrs, it is 35 man days. If 15 worked for 9 hrs, it is 15x9/8 = 16.875 man days. (Total 35+16.875 = 51.875 man days). Abbas.P.S
From India, Bangalore
sasikumar-p
Man days calculation for annual days. In case worked in 35 staffs means how many man days
From India, Bengaluru
KK!HR
1422

Eight hours of work is considered as a man day, so by calculating the total number of hours and dividing it by eight, the man-days can be calculated
From India, Mumbai
skhr07
6

you will have to calculate mandays like below

Arrive at the no of days worked by the company: total days in the month-weekend-national holidays
No.of worked days by the company*No of total employees-no of leave taken

Eg: 31 days in Jan'22-10 weekly off-1 national holiday= 20 working days

Mandays=20*1200-700=23300

From India, Chennai
Find answers from people who have previously dealt with business and work issues similar to yours - Please Register and Log In to CiteHR and post your query.




About Us Advertise Contact Us Testimonials
Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.