Warning: preg_replace(): Empty regular expression in [path]/showthread.php on line 2381

Warning: preg_replace(): Empty regular expression in [path]/showthread.php on line 2381

Warning: preg_replace(): Empty regular expression in [path]/showthread.php on line 2381
BOCW Act - Building and Other Construction Workers Rules - PPT Download - CiteHR

No Tags Found!

SH

Shai89308

Executive Hr

AS

Ammu Shanvi

Human Resource

GS

G SHASHI KRISHNA

Senior Manager - Hr

AH

Aizant HR

Human Resources

MA

MARSHAL

Safety Officer

AK

Anish Katoch

Hr Executive

PR

PranjalR

Hr Recruiter

AP

Alka Pal

Hr Executive

Karthikeyan8195

Management Consultant

MK

Mohit Kumar Puri

Head Marketing

AU

Austex

Accounts Manager


boss2966
1165

I am herewith attaching the ppt presentation on Building and Other construction Workers Act, 1996 and Building and Other Construction Workers Rules, 1998 for your ready reference. Please make your comments without fail so that any improvement can be made in future.
From India, Kumbakonam
Attached Files (Download Requires Membership)
File Type: ppt BOCW Acts & Rules.ppt (479.0 KB, 19572 views)

amirtha12varshini
19

Dear Mr.Bhaskar
No words to say.. Really Fantastic and easily understandable..In Exemption wherever factories act and Mines act under use this BOCW act is not applicable is it right?
Thank you for Posting
Regards
varsha

From India, Coimbatore
boss2966
1165

Thank you Varsha for your Valuable comments
In case the construction work is being carried out inside the premises of Factories or mine campus then there will only be Factories Act and Mines Act applicable and we need not to maintain the BOCW Act, as the same is being covered by the ibid act.
BOCW Act carries some technical aspects. As that is covered in Factories act and Mines Act, it is considered not required to be maintained. (Only form Nos. are being changed otherwise all are same).

From India, Kumbakonam
avsjai
456

Dear Bhaskar An excellent prersentation covering all the key points. My special appreciation to you. Regards AVS
From India, Madras
boss2966
1165

You are welcome Mr. Kannan. You can check my earlier thread also on Industrial Relations and Dispute too.
From India, Kumbakonam
n_k_lenka
1

Dear All,
I am in doubt over Factory & BOCW Acts. Can any one help me to clear my doubts on the followings:-
1. Whether Factory & BOCW Act will applicable in the expansion project of a running factory?
2.For any alteration or modification of a running factory (covered under Factory Act) needs the approval of Chief Inspector of Factories of the respective states. But in the approval it self it has noted that before construction CESS must be deposited under CESS ACT 1996. I am not able to understand the meaning & whether any Cess Act 1996 is there?
3. Prior to Oct'10 our factory (NFL) was under State Authority. None of the authorities were asking for BOCW cess. From Oct'10 our factory covered has under Central Govt. Now the state labour authorities asking for compliance of BOCW Act. Kindly express your expert opinion to tackle the issue.
Thanking you all in advance.
T/R
lenka

From India, Panipat
boss2966
1165

Dear Lenka

In which state your factory located.

You consult your factories inspector as well as Labour Commissioner about this doubt.

Because Once Factories Act is implemented there the BOCW act will get ceased. Once the Factory fencing is made excluding the expansion project then Factories Act is not applicable and only BOCW will be applicable to that expansion project.

But the construction area falls within the factory premises then BOCW Act cannot be applicable and only Factories Act will be applicable.

That's the reason Factories Inspector is given instruction for remitting the Cess as per the contract value in initial stage itself.

Eventhough you make payment it will be reimbursed by your principal employer. So you can pay the same after taking the concurrence from your client (for reimbursement purpose).

Now for this construction work you must apply to Central labour Office and not state Labour Office. Please check and apply for licence.

Hope I have cleared your doubts

All the best

From India, Kumbakonam
KSGopal
9

Dear Mr. Bhaskar,
Very impressive & nice presentation! Keep adding value!
However, the exception clause covers the following.
"The exception made is only in respect of residential houses for own purpose constructed with a cost not exceeding Rs. 10 lakh and such other activities to which the provisions of Factories Act, 1948 and Mines Act, 1952 apply."
Your views pl.
Thanks,
Gopal

From India, Jaipur
boss2966
1165

Thank you Mr. Gopal for your Valuable comments.
If the construction activities carried out inside the Factories and Mines Premises then the BOCW Act will not be applicable and for Residential Houses for Own purpose where the cost of construction is less than Rs.10,00,000/- also having the exemption to get covered in BOCW Act.

From India, Kumbakonam
korgaonkar k a
2555

Thank you very much Dear Bhaskar. It is really a master piece. With your permission I wish to use this ppt. Up till now I have given talks / lectures on this subject. But now I wish to give presentations with this tool given by you. Kindly permit. It's your creature. Thanks again.
keshav korgaonkar
http://www.shantadurgaent.com,Welcome To Shantadurga Enterprises
Cell: +91 9967516383

From India, Mumbai
Find answers from people who have previously dealt with business and work issues similar to yours - Please Register and Log In to CiteHR and post your query.





About Us Advertise Contact Us Testimonials
Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.