Dear All, Good Morning !! I need KPI with parameters.Which is in use in manufacturing industries right now? Kindly help. Regards, mili
From India, Vadodara
From India, Vadodara
Dear Mili,
You could have checked this forum before raising this query. Anyway click the following links:
https://www.citehr.com/450241-proces...ml#post2023422
https://www.citehr.com/259167-pms-wo...-training.html (check the entire thread)
Ok...
Dinesh V Divekar
From India, Bangalore
You could have checked this forum before raising this query. Anyway click the following links:
https://www.citehr.com/450241-proces...ml#post2023422
https://www.citehr.com/259167-pms-wo...-training.html (check the entire thread)
Ok...
Dinesh V Divekar
From India, Bangalore
Dear Sir,
I have already check. It is not according to my parameters.I have required only KPI parameters.
Kind help.Which will be very useful & very simple.
I have not required 360 degree,balance scorecard.
Regards,
mili
From India, Vadodara
I have already check. It is not according to my parameters.I have required only KPI parameters.
Kind help.Which will be very useful & very simple.
I have not required 360 degree,balance scorecard.
Regards,
mili
From India, Vadodara
I had prepared this for our company; hope you will have an idea for you from this further need suggestion from all for any changes, modification and improvement. R.Malik
From India
From India
Dear Mr R Malik,
Thanks for sharing the document. It is well prepared. However, I have small suggestion. In the last column i.e. in column 4, you have given weight. We need to divide this weight in column 3 also. This will bring more accountability in each area of activity.
Thanks,
Dinesh V Divekar
I had prepared this for our company; hope you will have an idea for you from this further need suggestion from all for any changes, modification and improvement.
R.Malik
From India, Bangalore
Thanks for sharing the document. It is well prepared. However, I have small suggestion. In the last column i.e. in column 4, you have given weight. We need to divide this weight in column 3 also. This will bring more accountability in each area of activity.
Thanks,
Dinesh V Divekar
I had prepared this for our company; hope you will have an idea for you from this further need suggestion from all for any changes, modification and improvement.
R.Malik
From India, Bangalore
Dear Sir,
Many Thanks. I have prepared PMS for the same.Now i would like to do deep study for each department performance every month.
Am interested to do know what kind of common & serious mistakes each department may do.
I agree it's vary from company to company.Even though i need your best & very useful suggestions.
Thanks,
mili
From India, Vadodara
Many Thanks. I have prepared PMS for the same.Now i would like to do deep study for each department performance every month.
Am interested to do know what kind of common & serious mistakes each department may do.
I agree it's vary from company to company.Even though i need your best & very useful suggestions.
Thanks,
mili
From India, Vadodara