Dear All, Can you please tell me which details i need to take under BOCW act from contractors.
My is new startup company in building construction. We have different different contractors as per the site work.
What is the process i need to do under this act.
Regards,
Anuradha
From India, Pune
My is new startup company in building construction. We have different different contractors as per the site work.
What is the process i need to do under this act.
Regards,
Anuradha
From India, Pune
Dear AnuradhajI,
1.Timeline:Thirty days before the commencement of construction work
a.Documents Required: Form 1
b.Name of Return / Compliance: Notice of commencement of construction work
c.To be Sent to: Area Inspector who is Asst. Director (IS&H)
d.Name of the Statute:The Building and other Construction Workers Act, 1996
2. Timeline: With in sixty days from Commencement of work
a.Documents Required:
- Application for Registration in Form 1
- Registration Fees as applicable
- Form IV
- Possession Certificate
- List of Directors & Memorandum of Article
- Estimated cost of project
- Project Report
b.Name of Return / Compliance: Registration of construction workers
c.To be Sent to:Registering Officer of the Area who is Deputy Director (IS&H)
d.Name of the Statute:The Building and other Construction Workers Act, 1996
3. Timeline: Within thirty days of completion of the construction project
a.Documents Required:
- Demand Draft of 1% of the project cost excluding cost of land, plant & machinery
- Statement of Total amount
b.Name of Return / Compliance: Welfare of construction workers
c.To be Sent to:Registering Officer of the Area who is Deputy Director (IS&H)
d.Name of the Statute:The Building and other Construction Workers Welfare Cess Act, 1996
As a principal Employer you are liable to take Bocw Licence from your Contractors.
Regards,
Amit
From India, Delhi
1.Timeline:Thirty days before the commencement of construction work
a.Documents Required: Form 1
b.Name of Return / Compliance: Notice of commencement of construction work
c.To be Sent to: Area Inspector who is Asst. Director (IS&H)
d.Name of the Statute:The Building and other Construction Workers Act, 1996
2. Timeline: With in sixty days from Commencement of work
a.Documents Required:
- Application for Registration in Form 1
- Registration Fees as applicable
- Form IV
- Possession Certificate
- List of Directors & Memorandum of Article
- Estimated cost of project
- Project Report
b.Name of Return / Compliance: Registration of construction workers
c.To be Sent to:Registering Officer of the Area who is Deputy Director (IS&H)
d.Name of the Statute:The Building and other Construction Workers Act, 1996
3. Timeline: Within thirty days of completion of the construction project
a.Documents Required:
- Demand Draft of 1% of the project cost excluding cost of land, plant & machinery
- Statement of Total amount
b.Name of Return / Compliance: Welfare of construction workers
c.To be Sent to:Registering Officer of the Area who is Deputy Director (IS&H)
d.Name of the Statute:The Building and other Construction Workers Welfare Cess Act, 1996
As a principal Employer you are liable to take Bocw Licence from your Contractors.
Regards,
Amit
From India, Delhi